Construction Phases

  • Phase 1: Site excavation and gabion foundation (2 weeks)
  • Phase 2: Wall frame and roof rafters (2 weeks)
  • Phase 3: Wattle weave and straw-clay insulation (1.5 weeks)
  • Phase 4: EPDM membrane and exterior render (1 week)
  • Phase 5: Living roof and solar installation (1 week)
  • Phase 6: Openings and interior finish (1 week)
  • Tool list: excavator, wire cutters, chainsaw, tampers, scaffolding
  • Critical path: excavation → gabions → frame → roof → shell